Most of these projects were performed under our Won and Run model. We support the full lifecycle, from opportunity analysis and proposal development through project execution, then integrate directly into the prime contractor’s key personnel as Project Manager, Quality Control Manager, Safety Coordinator, Environmental Manager, Scheduler, or Specifier.
Over the past six years, we have developed or led 299 federal proposals covering design-build, repair, modernization, emergency relief, and civil works. These include MATOC, SATOC, MACC, IDIQ, and standalone procurements across DoD, USACE, NAVFAC, USDA Forest Service, National Park Service, and other federal agencies.
We don’t just write the proposal. We step into the prime’s key roles and run the job. That real-world experience is what makes the technical volumes credible and the execution clean.
Contract No.: N6945025F0199
Location: Naval Support Activity (NSA) Mid-South, Millington, TN
Customer: NAVFAC Southeast
Period of Performance: February 6, 2025 to February 5, 2026
Initial Contract Value: $847,271
Final Contract Value: $847,271
Roles Performed by MCB: Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, and Scheduler
Project Highlight: Midcon Builds served as Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, and Scheduler for this NAVFAC Southeast project at NSA Mid-South. From planning and project controls through quality, safety, and environmental compliance, MCB provided leadership and oversight throughout project execution, helping ensure successful delivery and compliance with federal construction requirements.
Contract No.: N6945024F0911
Location: NSA Mid-South, Millington, TN
Customer: NAVFAC Southeast
Period of Performance: September 24, 2024 to June 16, 2025
Initial Contract Value: $520,567
Final Contract Value: $520,567
Roles Performed by MCB: Project Manager, Superintendent, Quality Control Manager, Safety Manager, Environmental Manager, and Scheduler
Project Highlight: Midcon Builds served as Project Manager, Superintendent, Quality Control Manager, Safety Manager, Environmental Manager, and Scheduler for this NAVFAC Southeast project. MCB provided leadership and oversight across project planning, field operations, quality control, safety management, environmental compliance, scheduling, and project controls throughout execution. The project was successfully completed while maintaining compliance with NAVFAC construction standards, quality requirements, and project performance objectives.
Contract No.: 140P1424D0007 / 140P1424F0106
Location: Yellowstone National Park, West Yellowstone, MT
Customer: National Park Service
Period of Performance: July 2, 2024 to October 19, 2024
Initial Contract Value: $181,899
Final Contract Value: $181,899
Roles Performed by MCB: Preconstruction Project Manager, Quality Control Manager, Site Safety and Health Officer (SSHO), Environmental Manager, and Scheduler
Project Highlight: Midcon Builds served as Preconstruction Project Manager, Quality Control Manager, Site Safety and Health Officer (SSHO), Environmental Manager, and Scheduler for this National Park Service project within Yellowstone National Park. MCB provided leadership and oversight across project planning, quality assurance, safety management, environmental compliance, scheduling, and project controls throughout execution, helping support successful delivery within one of the nation's most environmentally and culturally significant federal assets.
Contract No.: 12445522F0159
Location: Monongahela National Forest, Webster County, WV
Customer: USDA Forest Service
Period of Performance: October 11, 2022 to September 7, 2023
Initial Contract Value: $203,926
Final Contract Value: $210,446
Roles Performed by MCB: Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, and Scheduler
Project Highlight: Midcon Builds served as Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, and Scheduler for this USDA Forest Service project within the Monongahela National Forest. MCB provided leadership and oversight across project planning, quality control, safety management, environmental compliance, scheduling, and project controls throughout execution. The project was successfully completed with limited contract value growth while maintaining compliance with USDA Forest Service requirements and project performance objectives.
Contract No.: 693C7319C000016
Location: Monongahela National Forest, White Sulphur Springs, WV
Customer: USDA Forest Service
Period of Performance: July 15, 2019 to July 9, 2020
Initial Contract Value: $886,680.21
Final Contract Value: $1,036,362.67
Roles Performed by MCB: Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, and Scheduler
Project Highlight: Midcon Builds served as Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, and Scheduler for this USDA Forest Service project within the Monongahela National Forest. MCB provided leadership and oversight across project planning, quality control, safety management, environmental compliance, scheduling, and project controls throughout execution. The project was successfully completed while supporting delivery of a federal construction contract exceeding $1 million in final value.
Contract No.: W9126G22C0008
Location: Brazos River Valley, Whitney Dam, Clifton, TX
Customer: U.S. Army Corps of Engineers (USACE)
Period of Performance: April 30, 2022 to May 10, 2023
Initial Contract Value: $463,494
Final Contract Value: $517,123
Roles Performed by MCB: Preconstruction Project Manager, Site Safety and Health Officer (SSHO), Environmental Manager, and Scheduler
Presentation takeaway: MCB provided preconstruction management, safety, environmental compliance, and scheduling services in support of this USACE project at Whitney Dam. Our team managed preconstruction planning, safety oversight, environmental requirements, and project controls throughout the period of performance, supporting successful execution and completion of a federally funded infrastructure project while maintaining control of cost and schedule.
Contract No.: 12343419C0001
Location: Monongahela National Forest, Elleber Knob, WV
Customer: USDA Forest Service
Period of Performance: September 21, 2019 to September 22, 2019
Initial Contract Value: $164,543.60
Final Contract Value: $169,643.60
Roles Performed by MCB: Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, and Scheduler
Project Highlight: MCB provided comprehensive project management, quality control, safety, environmental compliance, and scheduling services in support of this USDA Forest Service project within the Monongahela National Forest. Our team managed field operations, quality assurance, safety oversight, environmental requirements, and project controls throughout the short period of performance, supporting successful execution and completion while maintaining effective control of contract modifications.
Contract No.: 693C7320C000001
Location: Monongahela National Forest, White Sulphur Springs, WV
Customer: USDA Forest Service
Period of Performance: March 1, 2020 to September 30, 2021
Initial Contract Value: $2,184,616.30
Final Contract Value: $2,176,989.08
Roles Performed by MCB: Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, and Scheduler
Project Highlight: MCB provided comprehensive project management, quality control, safety, environmental compliance, and scheduling services in support of this USDA Forest Service project within the Monongahela National Forest. Our team managed project planning, field operations, quality assurance, safety oversight, environmental requirements, and project controls throughout the period of performance, supporting successful execution and completion of a contract valued at approximately $2.18 million.
Contract No.: FA481920C0044
Location: Tyndall Air Force Base, Panama City, FL
Customer: United States Air Force
Period of Performance: October 26, 2020 to September 23, 2021
Initial Contract Value: $579,646.11
Final Contract Value: $579,646.11
Roles Performed by MCB: Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, Scheduler, Specifier, and Design Project Manager
Project Highlight: MCB provided comprehensive design and construction management services in support of this United States Air Force project at Tyndall Air Force Base. Our team performed as Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, Scheduler, Specifier, and Design Project Manager, managing project planning, design coordination, quality assurance, safety compliance, environmental requirements, and project controls throughout the period of performance, supporting successful execution and completion.
Contract No.: W9127821R0013
Location: Lake Seminole, Chattahoochee, FL
Customer: United States Army Corps of Engineers (USACE)
Period of Performance: June 9, 2021 to September 23, 2021
Initial Contract Value: $168,033.00
Final Contract Value: $205,392.00
Roles Performed by MCB: Project Manager, Superintendent, Site Quality Control Manager, and Site Safety Representative
Project Highlight: MCB provided direct field leadership and project oversight in support of this USACE project at Lake Seminole. Our team performed as Project Manager, Superintendent, Site Quality Control Manager, and Site Safety Representative, managing on-site operations, quality control, safety compliance, and project execution throughout the period of performance, supporting successful completion while controlling cost growth from the initial contract value.
Contract No.: FA481921C0006
Location: Tyndall Air Force Base, Panama City, FL
Customer: United States Air Force
Period of Performance: May 3, 2021 to August 3, 2022
Initial Contract Value: $821,828.00
Final Contract Value: $857,215.86
Roles Performed by MCB: Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, Scheduler, Specifier, and Design Project Manager
Project Highlight: MCB provided comprehensive design and construction management services in support of this United States Air Force project at Tyndall Air Force Base. Our team performed as Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, Scheduler, Specifier, and Design Project Manager, managing project planning, design coordination, quality assurance, safety compliance, environmental requirements, and project controls throughout the period of performance, supporting successful execution and completion.
Contract No.: FA481921C0017
Location: Tyndall Air Force Base, Panama City, FL
Customer: United States Air Force
Period of Performance: August 11, 2021 to May 18, 2022
Initial Contract Value: $423,996.77
Final Contract Value: $423,996.77
Roles Performed by MCB: Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, Scheduler, Specifier, and Design Project Manager
Project Highlight: MCB provided comprehensive design and construction management services in support of this United States Air Force project at Tyndall Air Force Base. Our team performed as Project Manager, Quality Control Manager, Safety Manager, Environmental Manager, Scheduler, Specifier, and Design Project Manager, managing project planning, design coordination, quality assurance, safety compliance, environmental requirements, and project controls throughout the period of performance, supporting successful execution and completion.
Location: Port St. Joe, FL
Customer: Florida Department of Environmental Protection
Role: Second-tier subcontract
Work: Two new pile-supported ranger residences and Hurricane Michael restroom rebuild
Site: Coastal state park, environmental and QC controls
Jerry Tarley’s field experience was forged across multiple austere and high-stakes environments, including Afghanistan, Iraq, South Sudan, Kenya, Uganda, Somalia, Liberia, Djibouti, Aruba, Turks and Caicos, Antigua, the Marshall Islands, and Chad. These assignments spanned LOGCAP and other federal support programs, remote island installations, and complex construction operations under demanding logistical, security, and operational conditions.