Most of these projects were Won and Run projects for MCB. That means we identified the opportunity, sent an analysis to a Prime Contractor, wrote the proposal, provided a project estimate review, and performed in various key personnel positions, including Project Manager, Safety Coordinator, Quality Control Manager, Environmental Manager, Scheduler, Specifier, etc. for the Prime Contractor. Services were performed for several federal agencies, including USACE, NAVFAC, other Army and Navy Organizations, USAF, USFWS, USDA FS, and others.
Contract Number: 12445522F0159
Location: Monongahela National Forest, Webster County, WV
Customer: USDA Forest Service
Award Date: September 27, 2022
Project Start Date (NTP): October 11, 2022
Project Completed Date: September 7, 2023
Initial Contract Value: $203,926
Final Contract Value: $210,446
Positions Filled by MCB: PM, QCM, Safety Manager, Environmental Manager, Scheduler
Contract Number: 693C7319C000016
Location: Monongahela National Forest, White Sulphur Springs, WV
Customer: USDA Forest Service
Award Date: May 14, 2019
Project Start Date (NTP): July 15, 2019
Project Completed Date: July 9, 2020
Initial Contract Value: $886,680.21
Final Contract Value: $1,036,362.67
Positions Filled by MCB: PM, QCM, Safety Manager, Environmental Manager, Scheduler
Contract Number: W9126G22C0008
Location: Brazos River Valley Whitney Dam, Clifton, TX
Customer: US Army Corps of Engineers
Award Date: April 29, 2022
Project Start Date (NTP): April 30, 2022
Project Completed Date: May 10, 2023
Initial Contract Value: $463,494
Final Contract Value: $517,123
Positions Filled by MCB: Preconstruction PM, SSHO, Environmental Manager, Scheduler
Contract Number: 12343419C0001
Location: Monongahela National Forest, Elleber Knob, WV
Customer: USDA Forest Service
Award Date: August 20, 2019
Project Start Date (NTP): September 21, 2019
Project Completed Date: September 22, 2019
Initial Contract Value: $164,543.60
Final Contract Value: $169,643.60
Positions Filled by MCB: PM, QCM, Safety Manager, Environmental Manager, Scheduler
Contract Number: 693C7320C000001
Location: Monongahela National Forest, White Sulphur Springs, WV
Customer: USDA Forest Service
Award Date: October 29, 2019
Project Start Date (NTP): March 01, 2020
Project Completed Date: September 30, 2021
Initial Contract Value: $2,184,616.30
Final Contract Value: $2,176,989.08
Positions Filled by MCB: PM, QCM, Safety Manager, Environmental Manager, Scheduler
Contract Number: FA481920C0044
Location: Tyndall Air Force Base, Panama City, FL
Customer: United States Air Force
Award Date: September 28, 2020
Project Start Date (NTP): October 26, 2020
Project Completed Date: September 23, 2021
Initial Contract Value: $579,646.11
Final Contract Value: $579,646.11
Positions Filled by MCB: PM, QCM, Safety Manager, Environmental Manager, Scheduler, Specifier, Design PM
Contract Number: W9127821R0013
Location: Lake Seminole, Chattahoochee, FL
Customer: United States Army Corps of Engineers (USACE)
Award Date: May 26, 2021
Project Start Date (NTP): June 9, 2021
Project Completed Date: September 23, 2021
Initial Contract Value: $168,033.00
Final Contract Value: $205,392.00
Positions Filled by MCB: PM, Superintendent, site QC and Safety
Contract Number: FA481921C0006
Location: Tyndall Air Force Base, Panama City, FL
Customer: United States Air Force
Award Date: March 18, 2021
Project Start Date (NTP): May 03, 2021
Project Completed Date: August 03, 2022
Initial Contract Value: $821,828.00
Final Contract Value: $857,215.86
Positions Filled by MCB: PM, QCM, Safety Manager, Environmental Manager, Scheduler, Specifier, Design PM
Contract Number: FA481921C0017
Location: Tyndall Air Force Base, Panama City, FL
Customer: United States Air Force
Award Date: July 21, 2021
Project Start Date (NTP): August 11, 2021
Project Completed Date: May 18, 2022
Initial Contract Value: $423,996.77
Final Contract Value: $423,996.77
Positions Filled by MCB: PM, QCM, Safety Manager, Environmental Manager, Scheduler, Specifier, Design PM
Contract Numbers: 01A Ranger Residence Houses - 08A Beach Restrooms
Location: St. Joseph Peninsula, Port St. Joe, FL
Customer: 2nd Tier subcontractor for Florida State DEP
Award Date: March 31, 2021
Project Start Date (NTP): April 30, 2021
Project Completed Date: December 23, 2021
Initial Contract Value: $1,060,000.00 - $155,000.00
Final Contract Value: $1,187,055.92 - $146,671.28
Positions Filled by MCB: PM, QCM, Safety Manager
Afghanistan, Iraq, South Sudan, Kenya, Uganda, Somalia, Liberia, Djibouti, Aruba, Turks and Caicos, Antigua, Marshall Islands, Chad