This project involved a Won and Run approach where we developed the proposal, estimated the project scope, and acted as Project Manager, Safety Coordinator, Quality Control Manager, Environmental Manager, and Scheduler for the Prime Contractor at Yellowstone National Park, specifically at the West Entrance in Montana/Wyoming.
This task order was issued under the GAOA-funded NR MABO MATOC, and MidCon Builds also authored the original MATOC proposal. Under this same MATOC vehicle, the Prime Contractor (NNAC) has been awarded several projects, including:
The West Entrance boiler project, particularly the high-altitude hydronic boiler replacement, included the removal of the existing Munchkin boilers and the installation of new high-altitude rated Lochinvar Knight (KHB series) condensing boilers. The scope also comprised a Squire storage tank, Grundfos circulator pumps, expansion tanks, a chemical feed system, Distech ECLYPSE controls, and all necessary associated piping, valves, and venting. This work was conducted within a live, remote national park environment, presenting unique challenges such as seasonal access constraints, wildlife activity, and high-elevation performance requirements.
Ultimately, the YNP boiler replacement project was completed successfully, remaining on schedule and within budget.

New high-efficiency boiler system installed at the West Entrance facility, including piping, circulator pumps, expansion tank, and associated controls. Work completed under remote high-altitude conditions while maintaining schedule and operational continuity.

Installed Lochinvar boiler unit with new piping, valves, and chemical feed system. System designed and installed to meet high-elevation performance requirements and project quality standards.

West Entrance approach road at Yellowstone National Park. Project executed in a remote national park environment with seasonal access constraints, wildlife activity, and high-elevation performance requirements.

Manufacturer nameplate and certification data for the new boiler equipment, documenting rated capacity, pressure, and ASME certification for the high-altitude installation.

Close-up of boiler rating plate and certification labels confirming compliance with applicable codes and performance requirements for the Yellowstone installation.

New Lochinvar boiler and associated equipment staged and installed in the mechanical room. Installation sequenced to minimize disruption while meeting the project schedule.